Japan agrees second nuclear reactor life extension since Fukushima — Reuters

” Japan’s nuclear regulator on Wednesday approved an application by Kansai Electric Power Co Inc to extend the life of an ageing reactor beyond 40 years, the second such approval it has granted under new safety requirements imposed since the Fukushima disaster.

The move means Kansai Electric, Japan’s most nuclear-reliant utility before Fukushima led to the almost complete shutdown of Japan’s atomic industry, can keep No. 3 reactor at its Mihama plant operating until it is 60 years old in 2036.

The regulator granted the first such approval in June to Kansai Electric’s ageing reactors No.1 and 2 at its Takahama plant.

The Mihama No.3 reactor, which will turn 40 years old in December, has been shut down since 2011 and a restart will not happen before Kansai Electric carries out safety upgrades at a cost of about 165 billion yen ($1.51 billion). The upgrades involve fire proofing cabling and other measures and are planned to be completed in March 2020.

The regulator has been criticized for hastily approving the safety approval of reactors at the expense of safety.

Opinion polls consistently show opposition to nuclear power following Fukushima. Critics say regulators have failed to take into account lessons learned after a massive earthquake and tsunami caused meltdowns at the Fukushima Daiichi plant. ”

Reporting by Osamu Tsukimori, editing by Kenneth Maxwell

source

Cancer patient compensated for Fukushima work to sue Tepco — The Asahi Shimbun

” A 42-year-old man diagnosed with leukemia after working at the crippled Fukushima No. 1 nuclear plant plans to sue Tokyo Electric Power Co., saying the utility failed to take adequate precautions against radiation exposure.

He will also sue Kyushu Electric Power Co., operator of the Genkai nuclear plant in Saga Prefecture where he had also worked, in the lawsuit expected to be filed at the Tokyo District Court on Nov. 22.

The man, who is from Kita-Kyushu in Fukuoka Prefecture, will demand about 59 million yen ($541,000) in total compensation from the two utilities.

“TEPCO and Kyushu Electric, as the managers of the facilities, are responsible for the health of workers there, but they failed to take adequate measures to protect them from radiation exposure,” said one of the lawyers representing him.

“The man was forced to undergo unnecessary radiation exposure because of the utilities’ slipshod on-site radiation management, and as a result had to face danger to his life and fear of death,” the lawyer said.

The lawyers group said the man has a strong case, citing a ruling by labor authorities in October 2015 that recognized a correlation between his leukemia and his work in response to the 2011 Fukushima nuclear disaster.

It was the first time cancer was ruled work-related among people who developed the disease after working at the stricken Fukushima No. 1 nuclear plant.

The planned lawsuit will be the first legal action against TEPCO brought by an individual whose work-related compensation claim has already been granted.

Between October 2011 and December 2013, the man worked at the Fukushima No. 1 nuclear plant to set up a cover on the damaged No. 4 reactor building and perform other tasks.

The man also did regular maintenance jobs at the Genkai plant.

His accumulative radiation exposure at the two plants came to about 20 millisieverts.

He was diagnosed with acute myelocytic leukemia in January 2014. ”

source

Work starts in Fukushima on intermediate waste facility — The Asahi Shimbun

” The Environment Ministry on Nov. 15 started building a facility in Fukushima Prefecture that will store radiation-contaminated debris for up to 30 years, despite obtaining permission for only 11 percent of the site.

The 16-square-kilometer storage facility is expected to hold up to 22 million cubic meters of materials contaminated by radioactive fallout from the disaster at the Fukushima No. 1 nuclear power plant in March 2011.

“I hope that you take pride in this project and cooperate to construct the facility,” Tadahiko Ito, a vice environment minister, told workers.

The facility, which will span the towns of Futaba and Okuma, is expected to start accepting, sorting and storing the debris in autumn 2017 at the earliest, more than two-and-a-half years later than the initial schedule of January 2015.

The project has been delayed because the ministry has faced difficulties buying or borrowing land for the project.

In fact, only 445 of the 2,360 landowners of plots at the site have agreed to sell or lend their properties to the ministry for the storage facility as of the end of October.

Many of the reluctant landowners, who possess 89 percent of the land, fear the contaminated waste will remain at the facility well beyond 30 years.

The government has worked out a bill stipulating that contaminated materials kept in the intermediate storage facility will be moved out of Fukushima Prefecture in 2045. However, the government has yet to decide on the location of the final disposal site.

A huge cleanup operation after the triple meltdown at the Fukushima nuclear plant collected tons of radioactive soil and debris.

In March 2015, the ministry borrowed land and created a “temporary storage place” within a 16-square-km site on an experimental basis.

However, only about 70,000 cubic meters of the waste has been taken to the temporary storage site as of the end of October. The remaining waste, exceeding 10 million cubic meters, is being tentatively stored at about 150,000 locations in the prefecture.

“If the transportation of contaminated materials to the intermediate storage facility proceeds, the waste currently stored in residential areas and at company compounds will be transported there,” said an official of the Fukushima prefectural government’s section in charge of decontamination. ”

source

Last cover removed from crippled reactor in Fukushima — The Asahi Shimbun; Crippled Fukushima reactor fully exposed for first time since meltdown — RT

The Asahi Shimbun:

” The No. 1 reactor at the Fukushima No. 1 nuclear power plant is completely exposed for the first time in five years after the last of the temporary protective covers for the crippled structure was removed Nov. 10.

The next step will be to extract nuclear fuel inside the reactor building, which was wrecked by a hydrogen explosion in the early stages of the March 2011 nuclear disaster.

The covers were installed the following October as a temporary measure against the spread of radioactive substances after the triple meltdown triggered by the Great East Japan Earthquake and tsunami.

A large crane lifted off the 20-ton cover, the last of the 18 panels installed, around 6 a.m. on Nov. 10.

Plant operator Tokyo Electric Power Co. began removing the covers one by one in September.

The 392 fuel assemblies are stored in the spent nuclear fuel pool inside the building. Melted fuel also remains inside the reactor.

TEPCO will assess the state of the reactor building’s interior in efforts to remove debris from the collapse of a roof over the spent nuclear fuel pool.

It will take precautions to prevent dust containing radioactive substances from being stirred up by shrouding the reactor building with tarpaulins. ”

by Kohei Tomida

source with aerial view video of uncovered Unit 1 reactor

* * *

RT:

” Fukushima’s Nuclear Plant reactor No. 1 has been fully exposed for the first time since the March 2011 tragedy, after the utility company safely removed the last cover sheet of the temporary protective construction.

Tokyo Electric Power Co. (TEPCO) used an industrial crane to lift the last of its 18 protective panels Thursday. Each of the panels weighs around 20 tons and measure 23 by 17 meters.

The protective cover was erected in October 2011 as a temporary measure to halt a radiation leak following a meltdown caused by a powerful earthquake and tsunami in March 2011. The dismantling of the panels started in July 2015 and was concluded on Thursday.

At Unit 1, rubble from the damaged building caused by the hydrogen explosion remains scattered and needs to be removed. The entire site is highly contaminated and will now be covered with tarpaulins to avoid the spread of radioactive waste. TEPCO is using anti-scattering agents to keep the dust down. Small pieces of rubble that can create dust are being vacuumed up while mist sprinklers are being used inside the building to keep radiation under control.

TEPCO next plans to remove 392 fuel assemblies from the spent pool and clean out the melted nuclear fuel from inside the building, NHK news reported. The utility company is assessing the level of radiation before continuing the cleanup process.

Scientists are also installing the necessary equipment to complete fuel extraction which will only start in four years. Fuel removal from Unit 1’s depleted fuel pool is scheduled to begin around March 2021, according to TEPCO’s Mid- and Long-Term Roadmap that was revised in June 2015.

In March 2011, a tsunami destroyed emergency generators at the plant. They had been cooling the reactors. The tsunami led to three nuclear meltdowns and the release of radioactive material. In Reactor 1, overheating caused the creation of hydrogen gas. On March 12, an explosion in Unit 1 destroyed the upper part of the building.

TEPCO’s decommission plan for the Fukushima nuclear power plant implies at least a 30-40 year period before the consequences of the meltdown are fully eliminated. So far the clean-up efforts have already cost Japan in excess of $21 billion. According to the latest estimates from the Ministry of Economy, Trade and Industry, the decommissioning costs will top $105 billion. ”

source

Scrapping of Monju would mean disposal of 760 tons of radioactive sodium, MOX fuel — The Japan Times

” About 760 tons of radioactive sodium remain in the piping and other equipment of the trouble-prone Monju prototype fast-breeder nuclear reactor, which may be ordered decommissioned, it was learned Sunday.

It has not been decided how to dispose of the radioactive sodium, said sources at the Japan Atomic Energy Agency, the operator of Monju. If the government decides to scrap the reactor, sodium disposal is expected to be a difficult challenge.

Sodium is used as a coolant at Monju, while water is used at conventional nuclear reactors. Sodium is a tricky chemical element that burns intensely if it comes into contact with air or water.

According to the agency, the Monju reactor has some 1,670 tons of sodium. Radioactive substances are contained in 760 tons of the total as it circulates inside the reactor vessel.

The Monju reactor needs to be drained of the sodium if it is to be demolished.

Radioactive and chemically active sodium has to be sealed in containers. There is no precedent of radioactive sodium disposal in Japan.

“We plan to consider the method of disposal if a decision is made to decommission (Monju),” an official said.

Monju, located in Tsuruga, Fukui Prefecture, is a core facility in Japan’s nuclear fuel cycle policy because, if running properly, the reactor produces more plutonium than it consumes.

More than ¥1 trillion, mostly from state budgets, has been invested in Monju. But the 280,000-kw reactor has operated for only 250 days since it reached criticality, or a self-sustained nuclear fission chain reaction, for the first time in April 1994, due to a raft of problems, including maintenance flaws, a sodium leak and fire and attempted coverup.

In November 2015, the Nuclear Regulation Authority advised the government to replace the operator of Monju. The government is carrying out a thorough review of the Monju project, including the possibility of decommissioning the reactor.

The disposal of the mixed-oxide, or MOX, fuel used at Monju is another significant issue. The amount of MOX fuel, a blend of uranium and plutonium recycled from spent nuclear fuel, that needs to be disposed of is estimated at 21 tons, but Japan is not equipped to carry out its disposal.

One option is to consign the disposal to a foreign country and receive the return of uranium and plutonium after the processing, along with radioactive waste.

But the agency’s cost estimate of ¥300 billion for decommissioning Monju does not include the expense of the overseas entrustment of MOX fuel disposal.

The agency aims to entrust France with the disposal of some 64 tons of MOX fuel that has been used at its Fugen advanced converter reactor, but no contract has been concluded. The Fugen reactor, also in Tsuruga, is slated to be decommissioned.

Spent MOX fuel contains larger amounts of highly toxic radioactive substances than spent uranium from conventional reactors.

The disposal of radioactive sodium and MOX fuel at Monju is emerging as an additional and difficult challenge for the government at a time when the final disposal site has not been decided for high-level radioactive waste from nuclear plants across Japan. ”

Jiji

source

*Joint appeal opposing the Indo-Japan Nuclear Cooperation Deal — Change.org

This petition was delivered to Japanese Prime Minister Shinzo Abe  and Indian Prime Minister Narendra Modi.

” We strongly oppose the signing of the India-Japan Nuclear Cooperation Agreement (hereafter: ‘the Agreement’) during the Indian Prime Minister Mr. Modi’s upcoming visit to Japan, expected to be in mid November this year.

The purpose of this Agreement is to allow Japan to export nuclear technology to India, a country that has not signed the Non-Proliferation Treaty (NPT) and in fact possesses nuclear weapons. With the cooperation of Japan, the only country that has experienced wartime nuclear attack, this Agreement will enable India to build nuclear reactors and it is believed it will also allow India to extract plutonium from spent fuel rods used in these reactors. With no effective international safeguards, there is a possibility that this plutonium could be used for military purposes. The already weak international non-proliferation regime, with NPT at its center, will be severely undermined with the legitimization of India’s nuclear weapons, which is, in effect what Japan is doing by signing this Agreement.

It is clear that by signing the Agreement, Japan will negate all its efforts towards global nuclear disarmament and abolition of nuclear weapons, based on its experiences of Hiroshima and Nagasaki. Since September this year, tensions between nuclear-armed Pakistan and India over Kashmir have been boiling over, and the danger of a nuclear war erupting is escalating. It is clear that signing the Agreement this November will only increase the military tensions in South Asia.

Furthermore, the nuclear accident which shock the world at Fukushima Daiichi, is by no means over. The moral integrity of the Japanese government is being called into question globally as it tries to peddle its nuclear technology, not just to India, but around the world, when the victims of Fukushima have not even been compensated.

In India, citizens who are concerned about the dangers of nuclear power have mounted large-scale protests, which have been met with brutal repression. Compensation for land acquisition, safety measures in case of accidents, evacuation plans and general compensation is woefully inadequate.

The Japanese government, which has refused to release contents of the Agreement for the reason that it was under negotiation, is now preparing to force through the signing of the Agreement. This Agreement is highly problematic, as we have described above.

We strongly urge both governments not to sign the Agreement and to stop negotiations immediately.

Request

Not to sign the India-Japan Nuclear Cooperation Agreement and to stop negotiations immediately.

Campaign Opposing the India-Japan Nuclear Cooperation Agreement 2016  “

source with Japanese version