Study: Possible water problem at storage sites in Fukushima — The Asahi Shimbun

” Bags of radiation-contaminated soil could be sinking into the ground at temporary storage sites in Fukushima Prefecture, allowing water to accumulate within instead of flowing to outside tanks for testing, the Board of Audit said.

No confirmation has been made that the ground at the sites is actually sinking or if contaminated water has pooled inside. But Board of Audit officials are asking the Environment Ministry to consider additional safety measures if signs indicate that this is actually occurring.

The board’s study focused on 34 of the 106 temporary storage sites that the Environment Ministry set up for soil removed through decontamination work after the disaster in March 2011 unfolded at the Fukushima No. 1 nuclear power plant.

Construction of the storage sites started in 2012, and the transfer of contaminated soil to these facilities was completed in 2015.

The temporary storage sites were designed to have a slight mound on the ground in the center to allow water from the bags to flow down into surrounding collection tanks for periodic measurements of radiation levels.

Internal Environment Ministry guidelines called for this setup at storage sites containing bags that are not waterproof.

The Board of Audit studied 34 temporary storage sites where the bags are not waterproof. These bags were piled five deep or higher at those sites.

The study showed that at 31 of the sites, the weight of the bags may have not only flattened the mound in the center, but it also could have created an indent in the ground where the leaking water could accumulate.

If the water does not flow to the tanks, it will be difficult to determine the radiation levels.

The study also noted that the foundations at the sites were soft to begin with and may be unable to support the bags of soil. The sinking phenomenon could worsen as time passes.

The Environment Ministry played down the risk of the water contaminating areas around the storage facilities.

“Even if the ground has sunk, the structure is designed so water does not leak outside the site,” a ministry official said. “Eventually, the water should collect in the tanks. We will make every effort to oversee the sites as well as use waterproof bags as much as possible.”

A total of 4.16 billion yen ($40 million) was spent to construct the 31 temporary storage sites.

The Environment Ministry designed the temporary storage sites under the precondition they would be used for only three years and then removed. For that reason, measures were not taken to strengthen the foundations to prevent the ground from sinking, even if soft farmland was chosen for a site.

The plan is to eventually return the land where the temporary storage sites have been built to its original state and return it to the landowners.

However, the Board of Audit’s study adds another concern for residents, many of whom had opposed construction of the temporary storage sites in their neighborhoods.

Toshio Sato, 68, has evacuated to Fukushima city from his home in Iitate village, where four of the possible problem storage sites are located.

“There are some people who want to resume growing rice once they return home,” Sato said. “If water is accumulating, there is the possibility it could unexpectedly overflow into surrounding areas. The concerns just seem to emerge one after another.”

The government plans to lift the evacuation order for a large part of Iitate in March 2017. ”

by Kosuke Tauchi, Shoko Rikimaru, Kenji Izawa and Akifumi Nagahashi

source

Fukushima Unit 2 containment repair research underway — SimplyInfo

” IRID announced details of work that is now underway to determine if a method for repairing the unit 2 suppression chamber might work.

IRID determined based on previous investigations that there may be a hole or series of holes of around 50mm in the unit 2 suppression chamber. Current research work will determine if filling that structure with concrete would work. The process that would be used and the extent of the research work is significant.

The proposed plan would use a concrete pump truck with a 5 inch diameter flexible hose to inject concrete into the suppression chamber. Initial work took place at the Ando Hazama Technical Research Institute (Tsukuba City, Ibaraki Prefecture) on October 15th.

It does appear they were successful in layering the concrete mixture and having it sink properly in the bottom of the suppression chamber tube. A 28 day pressure test will be conducted to assure the concrete properly plugs the leak. Future work may be conducted at the new decommissioning research center at Naraha. ”

by SimplyInfo

source with construction illustration and photos

Residents who fled Fukushima meltdown fear return to ghost town — Bloomberg

” Weed-engulfed buildings and shuttered businesses paint an eerie picture of a coastal Japanese town abandoned after a monstrous earthquake and tsunami triggered meltdowns in the Fukushima nuclear plant.

Namie, one of the communities hardest hit by the 2011 disaster, had 21,000 residents before they fled radiation spewing from the reactors eight kilometers (five miles) away. Prime Minister Shinzo Abe is now looking to repopulate the town as early as next year, a symbolic step toward recovery that might also help soften opposition to his government’s plan to restart Japan’s mostly mothballed nuclear industry.

“The national and local governments are trying to send us back,” said Yasuo Fujita, 64, a sushi chef who lives alongside hundreds of other Fukushima evacuees in a modern high rise in Tokyo more than 200 kilometers away. “We do want to return — we were born and raised there. But can we make a living? Can we live next to the radioactive waste?”

So far few evacuees are making plans to go back even as clean-up costs top $30 billion and Abe’s government restores infrastructure. That reluctance mirrors a national skepticism toward nuclear power that threatens to erode the prime minister’s positive approval ratings, particularly in areas with atomic reactors.

Mothballed Reactors

Officials in his government are calling for nuclear power to account for as much as 22 percent of Japan’s electricity supply by 2030, nearly the same percentage as before the Fukushima meltdown, in part to help meet climate goals. Only two of the nation’s 42 operable nuclear plants are currently running, leaving the country even more heavily reliant on imports of oil and gas.

A poll published by the Asahi newspaper this week found 57 percent of respondents were opposed to restarting nuclear reactors, compared with 29 percent in favor. One of Abe’s ministers lost his seat in Fukushima in an upper house election in July, and the government suffered another setback when an anti-nuclear candidate won Sunday’s election for governor of Niigata prefecture, home to the world’s largest nuclear plant.

Some 726 square kilometers — roughly the size of New York City — of Fukushima prefecture remain under evacuation orders, divided by level of radioactivity. While the government is looking to reopen part of Namie next year, most of the town is designated as “difficult to return to” and won’t be ready for people to move back until at least 2022.

“We must make the area attractive, so that people want to return there,” Reconstruction Minister Masahiro Imamura said this week. “I want to do everything I can to make it easy to go back.”

Workers are cleaning by scraping up soil, moss and leaves from contaminated surfaces and sealing them in containers. Still, the operation has skipped most of the prefecture’s hilly areas, leading to fears that rain will simply wash more contamination down into residential zones. Decommissioning of the stricken plant itself is set to take as many as 40 years.

The bill for cleaning up the environment is ballooning, with the government estimating the cost through March 2018 at $3.3 trillion yen ($32 billion). That’s weighing on Tokyo Electric Power Co. Holdings Inc., which is already struggling to avoid default over decommissioning costs.

“They are spending money in the name of returning things to how they were” without having had a proper debate on whether this is actually possible, said Yutaka Okada, senior researcher at Mizuho Research Institute in Tokyo. “Was it really right to spend this enormous amount of money?”

Namie officials, operating from temporary premises 100 kilometers away in the city of Nihonmatsu, are plowing ahead with preparations. A middle school in the town is scheduled for remodeling to add facilities for elementary pupils — even though they expect only about 20 children to attend. Similar efforts in nearby communities have had limited success.

Only 18 percent of former Namie residents surveyed by the government last year said they wanted to return, compared with 48 percent who did not. The remainder were undecided.

Staying Put

Fujita, the sushi chef, has joined the ranks of those starting afresh elsewhere. He opened a seafood restaurant near his temporary home last year, and is buying an apartment in the area. In a sign the move will be permanent, he even plans to squeeze the Buddhist altar commemorating his Fukushima ancestors into his Tokyo home.

For those that do return, finding work will be a headache in a town that was heavily dependent on the plant for jobs and money.

Haruka Hoshi, 27, was working inside the nuclear facility when the earthquake struck, and she fled with just her handbag. Months later she married another former employee at the plant, and they built a house down the coast in the city of Iwaki, where they live with their three-year-old son. They have no plans to return.

“It would be difficult to recreate the life we had before,” she said. “The government wants to show it’s achieved something, to say: ‘Fukushima’s all right, there was a terrible incident, but people are able to return after five years.’ That goal doesn’t correspond with the reality.” ”

by Isabel Reynolds and Emi Nobuhiro

source

Prospect of Niigata nuke plant delay threatens Tepco’s Fukushima plans — Nikkei Asian Review

” TOKYO — The election of an anti-nuclear candidate as governor of Japan’s Niigata Prefecture could hit the finances of not only Tokyo Electric Power Co. Holdings but the public as well, as the utility is relying on a reactor restart in Niigata to cover Fukushima cleanup costs.

The central government reached an arrangement in 2014 to extend up to 9 trillion yen ($86.6 billion currently) in interest-free loans to pay for dealing with the fallout of the 2011 Fukushima Daiichi nuclear plant disaster. Of this, 5.4 trillion yen is to go toward compensating those affected, with Tepco and other power companies, including Kansai Electric Power and Chubu Electric Power, to repay the loans. Another 2.5 trillion yen is earmarked for decontamination work, with the costs to be recouped through the sale of Tepco shares held by the government.

But more than 6 trillion yen in compensation has been paid out so far, and cost overruns on decontamination are seen as all but certain. Decommissioning work at Tepco’s Fukushima plant, such as extracting fuel, falls outside the 9 trillion yen framework.

The 2 trillion yen Tepco had aimed to secure on its own to pay for scrapping the plant will be nowhere near enough. The utility and Japan’s industry ministry had counted on bringing the Kashiwazaki-Kariwa nuclear plant in Niigata Prefecture back online, which would improve Tepco’s earnings by 240 billion yen a year. But Gov.-elect Ryuichi Yoneyama has indicated that he is not amenable to a quick restart.

An expert panel set up by the ministry started discussing how to handle the additional costs this month. It laid out a scenario in which improved profit margins at Tepco via restructuring, along with profits from the Kashiwazaki-Kariwa facility, would be used to minimize the amount shouldered by taxpayers.

The longer it takes to restart the plant in Niigata, the larger the hit will be to Tepco’s available funding for Fukushima costs. Though the utility will squeeze out some money via internal reforms, Tepco may use rate hikes to pass on to the public what it cannot cover itself. Tepco and other utilities already have raised rates to recoup part of the compensation costs. A top industry ministry official indicated that rate increases will also be on the table to pay for decommissioning.

Power companies besides Tepco could be affected as well. Since many nuclear plants in eastern Japan use boiling-water reactors like those at the Kashiwazaki-Kariwa plant, further delays could hold up other reactor restarts in the region. ”

by Nikkei

source

Japanese anti-nuclear candidate wins election at site of world’s biggest atomic power station — The Guardian; Simply Info

” An anti-nuclear candidate has been elected in a region of Japan that houses the world’s biggest atomic power station, striking a blow to Tokyo Electric Power’s attempts to restart the plant in the wake of the Fukushima disaster.

Ryuichi Yoneyama, a doctor-lawyer who has never held office and is backed mostly by leftwing parties, won the race for governor of Niigata, north of Tokyo, Japanese media projected on Sunday. Shares in Tokyo Electric Power fell 8% on Monday after the news broke.

The vote was dominated by concerns about the future of the Kashiwazaki-Kariwa power station and nuclear safety more than five years after the Fukushima catastrophe. The result represents a challenge to the government’s energy policy.

“As I have promised all of you, under current circumstances where we can’t protect your lives and your way of life, I declare clearly that I can’t approve a restart,” the 49-year-old told supporters at his campaign headquarters.

Cheers of “Banzai!” erupted as media began projecting him the winner over former mayor Tamio Mori, 67, backed by prime minister Shinzo Abe’s pro-nuclear Liberal Democratic party (LDP).

Yoneyama had more than 500,000 votes to about 430,000 for Mori with 93% of the vote counted, public broadcaster NHK said. Voters opposed restarting the plant by 73% to 27%, according to an exit poll by the broadcaster.

Mori, a former construction ministry bureaucrat, apologised to his supporters for failing to win the election.

Yoneyama, who has run unsuccessfully for office four times, promised to continue the policy of the outgoing governor who had long thwarted the ambitions of Tepco, as the company supplying about a third of Japan’s electricity is known, to restart the plant.

Reviving the seven-reactor site, which has a capacity of 8 gigawatts, is key to saving the utility, which was brought low by the Fukushima explosions and meltdowns, and then the repeated admissions of cover-ups and safety lapses after the world’s worst nuclear disaster since Chernobyl in 1986.

Tepco, put under government control in 2012, is vital to Abe’s energy policy, which relies on rebooting more of the reactors that once met about 30% of the nation’s needs.

The election became a litmus test for nuclear safety and put Abe’s energy policy and Tepco’s handling of Fukushima back under the spotlight.

The government wants to restart units that pass safety checks, also promoting renewables and burning more coal and natural gas.

Only two of Japan’s 42 reactors are running, more than five years after Fukushima, but the Niigata plant’s troubles go back further.

Several reactors at Kashiwazaki-Kariwa have been out of action since an earthquake in 2007 caused radiation leaks and fires in a disaster that prefigured the Fukushima calamity and Tepco’s bungled response.

Yoneyama, who has worked as a radiological researcher, said on the campaign trail that Tepco didn’t have the means to prevent Niigata children from getting thyroid cancer in a nuclear accident, as he said had happened in Fukushima. He said the company didn’t have a solid evacuation plan.

The LDP’s Mori, meanwhile, was forced to tone down his support for restarting the plant as the race tightened, media said, insisting safety was the priority for Kashiwazaki-Kariwa, while promoting the use of natural gas and solar power in Niigata. ”

source

* * *

Read a relevant analysis of this situation by SimplyInfo – “Niigata Election Throws Wrench in Japan Nuclear Plans”

Increases in perinatal mortality in prefectures contaminated by the Fukushima nuclear power plant accident in Japan — Scherb et al.

” Abstract: Descriptive observational studies showed upward jumps in secular European perinatal mortality trends after Chernobyl. The question arises whether the Fukushima nuclear power plant accident entailed similar phenomena in Japan. For 47 prefectures representing 15.2 million births from 2001 to 2014, the Japanese government provides monthly statistics on 69,171 cases of perinatal death of the fetus or the newborn after 22 weeks of pregnancy to 7 days after birth. Employing change-point methodology for detecting alterations in longitudinal data, we analyzed time trends in perinatal mortality in the Japanese prefectures stratified by exposure to estimate and test potential increases in perinatal death proportions after Fukushima possibly associated with the earthquake, the tsunami, or the estimated radiation exposure. Areas with moderate to high levels of radiation were compared with less exposed and unaffected areas, as were highly contaminated areas hit versus untroubled by the earthquake and the tsunami. Ten months after the earthquake and tsunami and the subsequent nuclear accident, perinatal mortality in 6 severely contaminated prefectures jumped up from January 2012 onward: jump odds ratio 1.156; 95% confidence interval (1.061, 1.259), P-value 0.0009. There were slight increases in areas with moderate levels of contamination and no increases in the rest of Japan. In severely contaminated areas, the increases of perinatal mortality 10 months after Fukushima were essentially independent of the numbers of dead and missing due to the earthquake and the tsunami. Perinatal mortality in areas contaminated with radioactive substances started to increase 10 months after the nuclear accident relative to the prevailing and stable secular downward trend. These results are consistent with findings in Europe after Chernobyl. Since observational studies as the one presented here may suggest but cannot prove causality because of unknown and uncontrolled factors or confounders, intensified research in various scientific disciplines is urgently needed to better qualify and quantify the association of natural and artificial environmental radiation with detrimental genetic health effects at the population level. ”

by Hagen Heinrich Scherb, Dr rer nat Dipl-Math, Kuniyoshi Mori, MD, Keiji Hayashi, MD

read full study