Challenges ahead for debris removal at Fukushima — NHK World

” This year will mark the 7th anniversary of the nuclear accident at the Fukushima Daiichi plant that occurred in March, 2011. The plant’s operator is hoping to eventually remove fuel debris from the damaged reactors.

Fuel debris is a mixture of melted nuclear fuel and broken reactor parts. Removing the debris is considered to be the biggest hurdle to the decommissioning of the reactors.

Last year, Tokyo Electric Power Company, or TEPCO, investigated the inside of the containment vessels of 3 reactors and confirmed, for the first time, the existence of lumps that are believed to be fuel debris in the No.3 reactor.

TEPCO plans to conduct a fresh probe of the No.2 reactor this month to confirm whether a mass on the floor under the reactor, observed last year, is actually fuel debris.

The government and TEPCO aim to begin removing debris in 2021. They are planning to determine which reactor to start with, and how to conduct the procedure, during fiscal 2019.

Workers will try this year to figure out which details need to be considered in order to make the decision.

Removing the debris requires thorough safety measures. For example, radioactive materials must be prevented from spreading and workers must be protected from exposure to radiation.

This autumn, the operator also plans to start removing spent nuclear fuel rods from the storage pool of the No.3 reactor building. ”