Fukushima disaster sways former advocate of nuclear power — Bloomberg

” The man blocking the world’s largest nuclear plant says he grew opposed to atomic energy the same way some people fall in love.

Previously an advocate for nuclear power in Japan, Ryuichi Yoneyama campaigned against the restart of the facility as part of his successful gubernatorial race last year in Niigata. He attributes his political U-turn to the “unresolved” 2011 Fukushima Dai-Ichi disaster and the lack of preparedness at the larger facility in his own prefecture, both owned by Tokyo Electric Power Co. Holdings Inc.

“Changing my opinion wasn’t an instant realization,” Yoneyama said in an interview. “It was gradual. As people say, you don’t know the exact moment you’ve fallen in love.”

Yoneyama won’t support the restart of the Kashiwazaki-Kariwa plant in Niigata until an investigation is complete into the chain of events that resulted in the triple meltdown at Fukushima, which he plans to visit Wednesday. While utilities don’t need approval of local authorities to restart plants, Japanese power companies are tradition-bound not to move ahead until they get their consent.

Local Opposition

Yoneyama, a 49-year-old doctor and native of Niigata, is one of the highest-profile local opponents pitted against a political establishment led by Prime Minister Shinzo Abe, which sees nuclear power as crucial for the country’s long-term energy security and environmental goals. Regulations and public opinion are keeping nearly all of Japan’s atomic stations shut almost six years after the accident at Fukushima, where the search has barely begun for fuel that burned through to the bottom of the reactors.

“If the local governor remains firmly opposed to the restart, it will be very difficult for the reactors to come back online,” said James Taverner, an analyst at IHS Markit Ltd. “In addition to the local government, building the support and trust of local residents is key.”

A Kyodo News poll on the day of Yoneyama’s October election showed about 64 percent of Niigata voters opposed the restart of Kashiwazaki-Kariwa, known popularly as KK. The restart of the facility was one of the key issues in the race to replace Governor Hirohiko Izumida, who was famous for his tough stance on Tokyo Electric. He unexpectedly announced in August that he wouldn’t seek a fourth term.

To the residents of the prefecture, Yoneyama was the candidate who would make nuclear safety a priority, while his main opponent gave off the vibe that he was a member of the nuclear restarts camp, the former governor said by e-mail.

Switching Sides

In last year’s gubernatorial race for the southern prefecture of Kagoshima, where Kyushu Electric Power Co. operates the Sendai nuclear plant, a three-term incumbent was defeated by an opponent campaigning to temporarily close the reactors. A district court last year barred Kansai Electric Power Co. from running two reactors at its Takahama station in western Japan only weeks after they’d been turned back on.

Yoneyama supported bringing back online Japan’s reactors during his unsuccessful bid in 2012 for a seat in Japan’s lower house. The country was being forced to spend more on fossil fuel imports after the disaster, so restarting the plants was needed to help the economy recover, he said at the time.

Though Yoneyama’s position switch helped secure his first electoral victory after four failed campaigns for the country’s legislature, nuclear opponents see him driven by more than political opportunism.

“I had my reservations about Yoneyama,” said Takehiko Igarashi, an official at the Niigata division of the anti-nuclear group Nakusou Genpatsu. “But after he was vetted and endorsed by the Japanese Communist Party and other smaller parties that have an anti-nuclear slant, I knew that I could trust him.”

evTokyo Electric and Abe’s government see restarting KK as one way for Japan’s biggest utility to boost profits and help manage its nearly 16 trillion yen ($139 billion) share of the Fukushima cleanup. Resuming reactors No. 6 and No. 7 will boost annual profits by as much as 240 billion, the utility has said.

The economic argument, however, is beginning to hold less sway, with Yoneyama saying the benefits to the local economy are ‘overstated.’ While the prefecture risks missing out on 1.1 billion yen a year in government support without the restart, that represents a small slice of the prefecture’s budget, which tops 1 trillion yen, according to Yoneyama.

Abe, a strong backer of atomic power, leads a government aiming for nuclear to account for as much as 22 percent of Japan’s energy mix by 2030, compared with a little more than 1 percent now.

While restart opponents like Yoneyama demand the government guarantee the safety of the reactors, they’ve also criticized evacuation and emergency response plans as inadequate.

In his first meeting with Tokyo Electric executives since taking office, Yoneyama earlier this month told Chairman Fumio Sudo and President Naomi Hirose that he won’t support KK’s restart until a new evacuation plan is drawn up using the results of a Fukushima investigation. Tepco will fully cooperate with the probe and stay in communication with the governor, the company said in response to a request for comment.
“Once I realized that the Fukushima disaster couldn’t be easily resolved, of course my opinion changed,” Yoneyama said. “If another accident occurs, overseas tourism will become a distant dream. Even Japanese may flee the country.” ”

by Stephen Stapczynski and Emi Urabe

source

Japanese anti-nuclear candidate wins election at site of world’s biggest atomic power station — The Guardian; Simply Info

” An anti-nuclear candidate has been elected in a region of Japan that houses the world’s biggest atomic power station, striking a blow to Tokyo Electric Power’s attempts to restart the plant in the wake of the Fukushima disaster.

Ryuichi Yoneyama, a doctor-lawyer who has never held office and is backed mostly by leftwing parties, won the race for governor of Niigata, north of Tokyo, Japanese media projected on Sunday. Shares in Tokyo Electric Power fell 8% on Monday after the news broke.

The vote was dominated by concerns about the future of the Kashiwazaki-Kariwa power station and nuclear safety more than five years after the Fukushima catastrophe. The result represents a challenge to the government’s energy policy.

“As I have promised all of you, under current circumstances where we can’t protect your lives and your way of life, I declare clearly that I can’t approve a restart,” the 49-year-old told supporters at his campaign headquarters.

Cheers of “Banzai!” erupted as media began projecting him the winner over former mayor Tamio Mori, 67, backed by prime minister Shinzo Abe’s pro-nuclear Liberal Democratic party (LDP).

Yoneyama had more than 500,000 votes to about 430,000 for Mori with 93% of the vote counted, public broadcaster NHK said. Voters opposed restarting the plant by 73% to 27%, according to an exit poll by the broadcaster.

Mori, a former construction ministry bureaucrat, apologised to his supporters for failing to win the election.

Yoneyama, who has run unsuccessfully for office four times, promised to continue the policy of the outgoing governor who had long thwarted the ambitions of Tepco, as the company supplying about a third of Japan’s electricity is known, to restart the plant.

Reviving the seven-reactor site, which has a capacity of 8 gigawatts, is key to saving the utility, which was brought low by the Fukushima explosions and meltdowns, and then the repeated admissions of cover-ups and safety lapses after the world’s worst nuclear disaster since Chernobyl in 1986.

Tepco, put under government control in 2012, is vital to Abe’s energy policy, which relies on rebooting more of the reactors that once met about 30% of the nation’s needs.

The election became a litmus test for nuclear safety and put Abe’s energy policy and Tepco’s handling of Fukushima back under the spotlight.

The government wants to restart units that pass safety checks, also promoting renewables and burning more coal and natural gas.

Only two of Japan’s 42 reactors are running, more than five years after Fukushima, but the Niigata plant’s troubles go back further.

Several reactors at Kashiwazaki-Kariwa have been out of action since an earthquake in 2007 caused radiation leaks and fires in a disaster that prefigured the Fukushima calamity and Tepco’s bungled response.

Yoneyama, who has worked as a radiological researcher, said on the campaign trail that Tepco didn’t have the means to prevent Niigata children from getting thyroid cancer in a nuclear accident, as he said had happened in Fukushima. He said the company didn’t have a solid evacuation plan.

The LDP’s Mori, meanwhile, was forced to tone down his support for restarting the plant as the race tightened, media said, insisting safety was the priority for Kashiwazaki-Kariwa, while promoting the use of natural gas and solar power in Niigata. ”

source

* * *

Read a relevant analysis of this situation by SimplyInfo – “Niigata Election Throws Wrench in Japan Nuclear Plans”

DPJ leaders deny urging cover-up of Fukushima meltdown — The Asahi Shimbun

” Former government leaders vehemently rejected suggestions in a report that they were pulling the strings behind a suspected meltdown cover-up when the Fukushima nuclear disaster was unfolding in 2011.

The report, compiled by an investigation panel commissioned by Tokyo Electric Power Co., operator of the crippled nuclear power plant, said Masataka Shimizu, who was TEPCO president at the time of the accident, instructed employees not to use the term “meltdown,” leading to a delay in the official announcement.

But the report also implied that Shimizu was acting on orders from high up in the government.

Yukio Edano, who was chief Cabinet secretary of the Democratic Party of Japan-led government when the Great East Japan Earthquake and tsunami triggered the nuclear crisis on March 11, 2011, described the report as preposterous.

“As far as I know, it is unthinkable for government officials back then to ask TEPCO to do such a thing,” Edano, now the secretary-general of the opposition Democratic Party, told reporters on June 16.

He accused the panel of merely skimming the surface of the matter and sidestepping the truth behind the instructions to avoid using the term “meltdown.”

“It is utterly irresponsible for the panel to say that it did not uncover that (Shimizu) was instructed by who and what,” he said.

The third-party panel of legal experts said in the report released on June 16 that it can be assumed that Shimizu understood that he was requested by the prime minister’s office to seek its approval beforehand if the company were to announce the “meltdown.”

The panel also said it would be difficult to conclude that TEPCO’s delay in declaring the meltdown was a “deliberate cover-up.”

“Since TEPCO released information on radiation levels inside the reactors and other related data at that time, just not using the term meltdown cannot be described as an act of a deliberate cover-up,” the panel said.

TEPCO declared the meltdown at three reactors at the Fukushima No. 1 plant in May 2011, two months after it occurred.

According to the report, Shimizu entered the chief Cabinet secretary’s office, which is located at the prime minister’s office building, by himself on March 13, 2011. The following day, Sakae Muto, vice president of TEPCO, explained the conditions of the reactors at the plant.

During the news conference, Shimizu handed a memo to Muto through a TEPCO public relations official, telling him not to use the word “meltdown” on the instructions of the prime minister’s office, according to the panel.

Naoto Kan, who was prime minister at the time of the disaster, denied giving the instruction to TEPCO.

“I myself have never given directions to TEPCO not to use the expression ‘meltdown,’” Kan, a member of the Democratic Party, said in a statement.

One reason for the lack of clarity in the report is that Shimizu, who was interviewed twice for a total of four hours, said, “I do not remember very well” with regard to who gave what instructions.

Another TEPCO employee interviewed by the panel said Shimizu “was under tremendous pressure and must not have a detailed recollection.”

The panel interviewed about 60 former and current TEPCO officials but no government officials and bureaucrats who were involved in dealing with the crisis.

“Our authority to investigate is limited, and it is difficult (to uncover the entire truth) in such a short time,” said Yasuhisa Tanaka, the lawyer who headed the investigation.

Tanaka and another panel member, Zenzo Sasaki, a former prosecutor at the Tokyo District Public Prosecutors Office, were also in charge of the third-party investigation into the accident conducted in 2013.

That investigation, based on interviews of TEPCO officials, came under fire for “only arbitrarily presenting TEPCO’s argument that is convenient to the company.”

The findings by the latest panel showed TEPCO officials looking into the nuclear disaster were aware of Shimizu’s order not to use “meltdown,” but TEPCO’s in-house investigation team did not include it in its report in 2012, apparently believing it was not significant enough to mention.

“TEPCO’s efforts to share information inside the company were insufficient,” Tanaka said. “It lacked consideration for local governments, which should have been top priority.”

The revelation that Shimizu ordered the avoidance of “meltdown” fueled feelings of distrust toward TEPCO among local governments hosting TEPCO nuclear power plants.

“We are still in this stage of the investigation even five years after the accident,” said Toshitsuna Watanabe, mayor of Okuma, which co-hosts the crippled Fukushima plant.

Hirohiko Izumida, governor of Niigata Prefecture, home to TEPCO’s Kashiwazaki-Kariwa nuclear power plant, called for a further investigation to reveal the whole picture of the Fukushima disaster.

“We need to step up efforts to uncover what has not been sufficiently investigated before,” he said. “TEPCO, as an organization, should make a sincere response without hiding anything.”

The latest panel was established in March at the request of the Niigata prefectural government’s technology committee, which aims to determine why TEPCO waited until May 2011 to announce the triple meltdown.

TEPCO initially said it did not have the criteria for defining and determining a meltdown.

But it announced in February this year that the company “found” an in-house manual that explained whether a meltdown was taking place. ”

source

Utility head blamed for late mention of Fukushima ‘meltdown’ — The Daily Star; DPJ leaders deny urging cover-up of Fukushima meltdown — The Asahi Shimbun

The AP via The Daily Star:

” TOKYO: An outside investigation team appointed by the operator of Japan’s damaged Fukushima nuclear plant said Thursday that an instruction from the company’s then-president to avoid using the term “meltdown” delayed the full disclosure of the status of three reactors.

Tokyo Electric Power Co. described the condition of the three reactors as less serious “core damage” for two months after a March 2011 earthquake and tsunami destroyed the plant.

The panel of three TEPCO-commissioned lawyers said the company used the milder term despite knowing that the damage far exceeded its meaning, because of the instructions by then-President Masataka Shimizu. The report said he was apparently under pressure from the Prime Minister’s Office, but that the panel did not find direct evidence of that.

TEPCO reported to the authorities on March 14, 2011, that the damage, based on a computer simulation, involved 25 to 55 percent of the fuel but did not say it constituted a “meltdown,” the report said. The company’s internal manual defined a “meltdown” as a core condition with damage exceeding 5 percent of the fuel.

In May 2011, TEPCO finally used the description after another computer simulation showed fuel in one reactor had almost entirely melted and fallen to the bottom of the primary containment chamber, and that the two other reactor cores had melted significantly.

TEPCO has been accused of softening its language to cover up the seriousness of the disaster. But the investigation found TEPCO’s delayed acknowledgement did not break any law.

In the 70-page report, the lawyers said Shimizu instructed his deputy not to use the word “meltdown” during news conferences immediately after the crisis when officials were peppered with questions about the reactor conditions. TEPCO’s vice president at the time, Sakae Muto, had used the phrase “possibility of meltdown” until March 14, 2011.

Video of a news conference that day shows a company official rushing over to Muto when he was about to respond to a question about the conditions of the reactors, showing him a memo and hissing into his ear, “The Prime Minister’s Office says never to use this word.”

Yasuhisa Tanaka, the lawyer who headed the investigation, said interviews of 70 former and current TEPCO officials, including Muto and Shimizu, showed that Muto had planned to use the word “meltdown” until he saw the memo, which has since not been found.

“Mr. Shimizu’s understanding was the term ‘meltdown’ could not be used without permission from the Prime Minister’s Office,” Tanaka told a news conference at TEPCO headquarters. “The notion that the word should be avoided was shared company-wide. But we don’t believe it was a cover-up.”

The Nuclear and Industrial Safety Agency, Japan’s nuclear regulatory unit at the time of the accident, was also reluctant to use the word. Two spokesmen were replaced between March 12 and 13, 2011, after suggesting meltdowns had occurred.

Government and parliamentary investigations have suggested officials, seeking to play down the severity of the Fukushima Dai-ichi crisis, resisted using the term. Tanaka said his investigation, which did not interview government officials, could not track down what exactly happened between Shimizu and the Prime Minister’s Office.

The Prime Minister’s Office has denied putting any pressure on TEPCO and the safety agency over language. But previous investigations of the accident show it demanded they coordinate with the office and unify approaches before making any announcement.

TEPCO has said the delay in confirming the meltdown didn’t affect the company’s emergency response at the plant. Although the reactors have been stabilized significantly, the company is still struggling with the plant’s decades-long decommissioning.

Delays in the announcement of meltdowns surfaced earlier this year in a separate investigation in which TEPCO acknowledged that a company manual had been overlooked, reversing its earlier position that it had no internal criteria for a meltdown. TEPCO has eliminated the definition of a meltdown from the manual that was revised after the Fukushima accident. ”

source

* * *

The Asahi Shimbun:

” Former government leaders vehemently rejected suggestions in a report that they were pulling the strings behind a suspected meltdown cover-up when the Fukushima nuclear disaster was unfolding in 2011.

The report, compiled by an investigation panel commissioned by Tokyo Electric Power Co., operator of the crippled nuclear power plant, said Masataka Shimizu, who was TEPCO president at the time of the accident, instructed employees not to use the term “meltdown,” leading to a delay in the official announcement.

But the report also implied that Shimizu was acting on orders from high up in the government.

Yukio Edano, who was chief Cabinet secretary of the Democratic Party of Japan-led government when the Great East Japan Earthquake and tsunami triggered the nuclear crisis on March 11, 2011, described the report as preposterous.

“As far as I know, it is unthinkable for government officials back then to ask TEPCO to do such a thing,” Edano, now the secretary-general of the opposition Democratic Party, told reporters on June 16.

He accused the panel of merely skimming the surface of the matter and sidestepping the truth behind the instructions to avoid using the term “meltdown.”

“It is utterly irresponsible for the panel to say that it did not uncover that (Shimizu) was instructed by who and what,” he said.

The third-party panel of legal experts said in the report released on June 16 that it can be assumed that Shimizu understood that he was requested by the prime minister’s office to seek its approval beforehand if the company were to announce the “meltdown.”

The panel also said it would be difficult to conclude that TEPCO’s delay in declaring the meltdown was a “deliberate cover-up.”

“Since TEPCO released information on radiation levels inside the reactors and other related data at that time, just not using the term meltdown cannot be described as an act of a deliberate cover-up,” the panel said.

TEPCO declared the meltdown at three reactors at the Fukushima No. 1 plant in May 2011, two months after it occurred.

According to the report, Shimizu entered the chief Cabinet secretary’s office, which is located at the prime minister’s office building, by himself on March 13, 2011. The following day, Sakae Muto, vice president of TEPCO, explained the conditions of the reactors at the plant.

During the news conference, Shimizu handed a memo to Muto through a TEPCO public relations official, telling him not to use the word “meltdown” on the instructions of the prime minister’s office, according to the panel.

Naoto Kan, who was prime minister at the time of the disaster, denied giving the instruction to TEPCO.

“I myself have never given directions to TEPCO not to use the expression ‘meltdown,’” Kan, a member of the Democratic Party, said in a statement.

One reason for the lack of clarity in the report is that Shimizu, who was interviewed twice for a total of four hours, said, “I do not remember very well” with regard to who gave what instructions.

Another TEPCO employee interviewed by the panel said Shimizu “was under tremendous pressure and must not have a detailed recollection.”

The panel interviewed about 60 former and current TEPCO officials but no government officials and bureaucrats who were involved in dealing with the crisis.

“Our authority to investigate is limited, and it is difficult (to uncover the entire truth) in such a short time,” said Yasuhisa Tanaka, the lawyer who headed the investigation.

Tanaka and another panel member, Zenzo Sasaki, a former prosecutor at the Tokyo District Public Prosecutors Office, were also in charge of the third-party investigation into the accident conducted in 2013.

That investigation, based on interviews of TEPCO officials, came under fire for “only arbitrarily presenting TEPCO’s argument that is convenient to the company.”

The findings by the latest panel showed TEPCO officials looking into the nuclear disaster were aware of Shimizu’s order not to use “meltdown,” but TEPCO’s in-house investigation team did not include it in its report in 2012, apparently believing it was not significant enough to mention.

“TEPCO’s efforts to share information inside the company were insufficient,” Tanaka said. “It lacked consideration for local governments, which should have been top priority.”

The revelation that Shimizu ordered the avoidance of “meltdown” fueled feelings of distrust toward TEPCO among local governments hosting TEPCO nuclear power plants.

“We are still in this stage of the investigation even five years after the accident,” said Toshitsuna Watanabe, mayor of Okuma, which co-hosts the crippled Fukushima plant.

Hirohiko Izumida, governor of Niigata Prefecture, home to TEPCO’s Kashiwazaki-Kariwa nuclear power plant, called for a further investigation to reveal the whole picture of the Fukushima disaster.

“We need to step up efforts to uncover what has not been sufficiently investigated before,” he said. “TEPCO, as an organization, should make a sincere response without hiding anything.”

The latest panel was established in March at the request of the Niigata prefectural government’s technology committee, which aims to determine why TEPCO waited until May 2011 to announce the triple meltdown.

TEPCO initially said it did not have the criteria for defining and determining a meltdown.

But it announced in February this year that the company “found” an in-house manual that explained whether a meltdown was taking place. ”

source

Tepco seeks foreign seal of approval to restart nuclear plant — The Japan Times

” Tokyo Electric Power Co.’s invitation to the world’s top nuclear agency to review the safety of its Kashiwazaki-Kariwa facility signals the utility’s desire to win international backing to resume operations at the world’s largest atomic power plant.

Kashiwazaki is Tepco’s best bet of returning to nuclear power generation, after the plant was shuttered along with the rest of Japan’s nuclear capacity following the unprecedented meltdowns at the company’s Fukushima No. 1 plant in 2011.

Firing up its reactors would boost Tepco’s profit by as much as ¥32 billion a month, according to Tepco spokesman Tatsuhiro Yamagishi.

“They want a foreign seal of approval,” said Robert Dujarric, a director at the Institute of Contemporary Asian Studies of Temple University in Tokyo. “No one trusts what Tepco says. The only way they can convince Japanese residents that this is not risky is to get a foreign institution to certify them being acceptable.”

The International Atomic Energy Agency began its 11-day evaluation on Tuesday and will report its findings to Japan’s watchdog, the Nuclear Regulation Authority, which has the final say on a plant’s safety. A restart would still need local government approval, which presents difficulties as the region’s governor remains a vociferous critic of Tepco.

Tepco expects to spend at least ¥270 billion to bring Kashiwazaki back online, although it says the cost is a secondary consideration. What is needed and what the IAEA brings is the “knowledge, ingenuity, and engineering capabilities to get there,” Takafumi Anegawa, Tepco’s chief nuclear officer, told a news conference at the plant on Tuesday. “Randomly spending money doesn’t assure safety.”

The NRA has visited Kashiwazaki three times since agreeing to check its reactors in 2013, although it has not given a timeline for approval, according to Tepco’s Yamagishi. NRA spokesman Taro Komine declined to comment on Kashiwazaki and the IAEA’s safety study there.

The IAEA was created in 1957 and one of its goals is to promote the safe use of nuclear energy. Tepco, meanwhile, is struggling to convince the Japanese public of improvements in its attitudes to safety amid worker deaths and irradiated water leaks at the ruined Fukushima plant.

“Of course Tepco would like them to come online,” Tom O’Sullivan, founder of Tokyo-based energy consultant Mathyos, said by email. However, “I have normally categorized it as a plant that is extremely unlikely to come online. There is huge local opposition.”

Hirohiko Izumida, three-term governor of Niigata Prefecture where the plant is located, has said restarting Kashiwazaki shouldn’t even be considered until Tepco’s safety record and handling of Fukushima are properly reviewed.

Niigata Prefecture spokesman Kenji Kiuchi declined to comment on the governor’s opinion of the IAEA review.

Restarting Kashiwazaki would boost Prime Minister Shinzo Abe’s plan for nuclear energy to account for as much as 22 percent of the country’s total electricity supply by 2030.

Thus far, Kyushu Electric Power Co.’s Sendai reactors are the only ones to pass the NRA’s safety requirements and clear local courts. Kyushu is aiming to restart the two units this year. While the NRA judged two reactors at Kansai Electric Power Co.’s Takahama station as safe, legal hurdles have since obstructed any restart.

Tepco is seeking to restore two of the seven reactors at Kashiwazaki, which is located about 220 km northwest of Tokyo on coast of the Sea of Japan. Its only other nuclear plants are Fukushima No. 1, which is being decommissioned, and the nearby Fukushima No. 2 facility, which may be too tainted by its association with the 2011 disaster to ever restart.

In order to ensure Kashizawaki’s safety, Tepco says it has bolstered staff levels, built a 15 meter flood-prevention wall, and built a reservoir to store 20,000 tons of water to cool reactors in case of pump failures.

The IAEA said its primary focus will be assessing the plant’s internal operations. Three months after its review, the agency will send its report to Tepco, the NRA and the Ministry of Economy, Trade and Industry.

The review will not replace Japan’s regulatory process, said Peter Tarren, the IAEA’s team leader at Kashiwazaki. “Decisions about restarts of the plant are not the authority of the IAEA,” he said. ”

source

Tepco likely to set ‘autumn restart’ for Niigata N-plant — The Yomiuri Shimbun

” Tokyo Electric Power Co. is likely to set autumn as its target to restart the Kashiwazaki-Kariwa nuclear power plant in Niigata Prefecture, according to sources.

TEPCO will present to its main banks, as early as this month, a new funding plan to improve its critical cash flow situation. The utility intends to stipulate the target for restarting the plant in its reconstruction plan, which is scheduled to be reviewed in June.

TEPCO applied to the Nuclear Regulation Authority in September 2013 for permission to reactivate the Kashiwazaki-Kariwa plant. It believes the safety screenings of the Nos. 6 and 7 reactors are going smoothly, the sources said.

TEPCO is preparing to restart the Kashiwazaki-Kariwa plant in October or later, and plans to complete safety measures against fires and tsunami, currently underway, by autumn.

However, the smooth progress TEPCO ancitipates also depends on whether the NRA asks TEPCO to implement additional safety measures following the screenings, or if the NRA delays screenings of other nuclear plants that are being undertaken ahead of the Kashiwazaki-Kariwa plant.

In addition, Niigata Gov. Hirohiko Izumida remains cautious about the restart.

TEPCO established a new office in Niigata as a regional headquarters in April to seek the understanding of local residents on the plan to reactivate the plant. ”

source